On June 18, 2026, the Public Utility Commission of Texas (PUCT) approved two Electric Reliability Council of Texas (ERCOT) protocol revisions that establish a new “batch” study interconnection ...
Add Yahoo as a preferred source to see more of our stories on Google. Transmission power lines are connected to an electrical power substation in Plano. (2023 File Photo/Tom Fox) Data centers and ...
When the Electric Reliability Council of Texas designed its process for connecting big industrial users to the statewide grid, it envisioned receiving from eight to 15 such requests every three months ...
Data centers and other large electricity users wanting to connect to Texas' electrical grid will soon be evaluated in batches, starting with "batch zero" later this summer. The Public Utility ...